Abstract:Terraced fields is one of the basis measures on soil and water conservation construction, especially on the loess plateau, in which the amount of the sloping fields is 49.2% of the total fields. Along with the nation's starting the construction of soil and water conservation overall, and putting it into capital construction, to drawing up the quota of budgetary estimate of soil and water conservation is more and more important. Combining with drawing up the way of working out the budgetary estimate and the quota of budgetary estimate of initial design on soil and water conservation project of the Yellow river basin, the way of work out the budgetary estimate of terraced fields, and the calculated unit, subtitle installed, the step distant, manpower, mechanism and consume material delimited are discussed. It talked about the rate of drawn fee to the unit price and the unit price of the project. In order to test the reasonableness of the quota of budgetary estimate, an example are taken for analysis.